Pushing ahead at Putney

Putney Station is one of the busiest suburban commuter stations in London, with 18 trains per hour passing through it at off-peak times alone. More than 11 million people used the station in 2012-13, making it busier than the stations of several large cities.

The station opened when the Nine Elms to Richmond line came into service on 27 July 1846, and was rebuilt in 1885-6 when the tracks were quadrupled. 130 years later, Spencer Rail began work on an £8 million improvement programme in October 2012.

The redevelopment, scheduled for completion by Spring 2014, is being funded under the Department for Transport’s Access for All initiative.

Since the start of the project, Spencer Rail has been working on site to install three new lifts, expand the concourse area, build new ticket gates and install new toilets.

Now, as the project nears completion, Spencer Rail has carried out one of the most significant parts of the project.

A temporary footbridge with staircases, which were installed to maintain access to all platforms throughout the works, was removed three weeks ahead of schedule.

The primary objective of the works is to provide step-free access from the ticket office and concourse to the platforms at Putney Station for all passengers, in accordance with the Disability Discrimination Act 2005.

A secondary benefit of the scheme will be the increased concourse area, which will alleviate congestion at the gate-line.

As part of the work, a dispersal bridge has been installed which spans all tracks and includes three new lift shafts and staircases.

A 16-person lift now goes to each platform – platforms two and three will share the same lift. In addition, there are alterations to communications and passenger information systems and extensive new lighting, and there will be two new public toilets and one for staff.

The concourse now has a masonry and glazed façade and all structures are covered by metal profiled sheet roofing.

It will be increased in size by removing the existing rear wall (the east face) and extending the floor space by approximately 14 metres to the rear of the building.

This will make room for the gate-line to be moved away from the front entrance, thereby improving passenger flow at busy periods.

There have been significant alterations at platform level as well.

On Platform 1, the old platform canopy was demolished in order to make room for the new staircase.

The existing platform building and canopy on Platforms 2 and 3 were partially demolished as part of the works, as were the existing staircase and rooms beneath on Platform 4.

The new lift motor room has been located under the new staircase.

 

What’s left to do?

With project team working towards a completion date of 16 May, Spencer Rail is now putting the finishing touches to the station.

There is still a lot to do, including the completion of floor and wall finishes (mainly tiling) and the roof cladding. The lifts have to be commissioned, as do the new lighting, toilets and CCTV.

The previous customer information screens and PA system has to be reinstated.

Structurally, arches between the ticket office and the concourse will be opened up by removing several piers and the temporary access ramp will be removed so that the canopies and platform surfaces can be made good. With the new bridge open and the temporary one removed, life is getting back to normal for travellers from Putney.

All the work has been carried out without any additional closures other than those already planned for the whole line so, apart from having to use a temporary footbridge and make a few detours, passengers haven’t been unduly inconvenienced.

Step-free access will be fully in place by the middle of May and the team from Spencer Rail be satisfied with a job well done.