Pembroke Dock

Spencer Group were the main contractor on an innovative project at Pembroke Dock, West Wales for the local Port Authority at Milford Haven Port. The works involved upgrading the existing roll‐on/roll‐off facility to double the available capacity of the dock, by providing both upper and lower access to ferries.

Key Project Details

Client Milford Haven Port Authority
Duration 52 weeks
Location Milford Haven, Pembrokeshire
Contract Form ICE 5th Edition

Project Scope

The scope of works included the design and construction of an existing Roll On Roll Off (RoRo) linkspan facility at Pembroke Dock. Spencer Group engaged our specialist design partner MG Bennett to collaborate during the tender, design, construction and commissioning stages of the project. By drawing on the knowledge of two successful design and build delivery partners the design team were able to provide an efficient, effective and safe design which bettered the client’s original scope.

Due to the Pembroke Dock Ferry terminal being upgraded from a single deck to a double deck arrangement, Spencer Group were contracted to delivered the design, manufacture, construction, testing and commissioning of a new hydraulic controlled structure to operate the additional cylinders on the upper deck finger flaps, as well as replacing the existing hydraulic system which operated the lower deck. The scope included over 500 tons of structural steel and reinforced concrete structures to create an additional car deck, 3.5m diameter steel buoyancy ‘submarine’ tanks, fixed and moving link span together with hydraulically operated articulated ‘fingers’ to accommodate vessel berthing. Marine and dock piling included 762mm diameter steel tube piles up to 30m deep. This was all achieved whilst accommodating twice daily ferry operations, without any loss of ferry berthings.

The project involved

60m linkspan bridge
11 independently operated ‘finger flaps’

Outcome

The design team scope included understanding the existing RoRo methodology and incorporating that into the combined RoRo methodology for the double deck finger flaps. As the scope required no impact to the ferry operations the design methodology had to be phased to ensure sufficient time allowance was given to the commissioning of the systems. This involved extensive mechanical and electrical equipment and operation across site to ensure each element was successful.


Find out more about our Build, Industrial and Civils services

The project involved

5-span fixed jetty
marine and dock piling