Heaton Depot

The upgrade of Heaton Depot was required by Network Rail as part of the Intercity Express Programme (IEP) for the new fleet of Hitachi Super Express trains. The IEP programme involved the upgrade of 8 light maintenance depots on the East Coast Main Line, with works at each carried out in sequence to maintain the operational requirements of the ECML.

Key Project Details

Client Network Rail
Duration 8 months
Location Heaton Depot, Newcastle
Contract Form NR9

Project Scope

• Construction of Temporary Fuelling Facility to cater for HST Tanking and Refuelling
• Construction of 2No attenuation slabs (1 x 15m, 1 x 93m)
• Installation of new Ad Blue Pumphouse, dispensers and associated pipeworks and Isolation Valves
• Installation of additional refuelling dispensers and associated pipeworks
• Installation of new 150mm, 300mm and 600mm drainage to allow drainage attenuation and additional manholes
• Installation of additional CET modules
• Renew P-Way
• Installation of GRP Track Collector pans (5 x 15m pans) and drainage

The project involved

Zero accidents
48,000 hours worked

Outcome

Spencer Group were required to upgrade fuelling roads 1 & 2 whilst keeping the operational requirements of the depot at 100%. To facilitate this, a temporary fuelling facility was constructed prior to disruptive works being carried out and taking fuelling road 2 out of service for 30 weeks. The project was substantially completed 3 weeks earlier than programmed.

Collaboration between Spencer staff and the depot staff needed to be at its highest level at all times, with daily interaction involving all levels of depot staff, to ensure the safe working of depot workers during the evenings. The project won three successive Network Rail 'STAR' audits, testament to the 'safety first' attitude on site.


Find out more about our Rail services

The project involved

Depot maintained 100% operational during project
100% Network Rail Environmental and Safety Audit Award